Two Butterfly Valves, Extended Pipework and New ‘Ts’ fitted
Site Location – Old Admiralty Building, London, SW1
Contract Duration – For one evening/night
Pipe Freezing with Liquid Nitrogen
Highlights of Services Completed Included –
Our experienced engineers attended the prestigious site out of hours.
Firstly, to stop the pipework flow, we carried out eight pipe freezes – four on the LTHW pipe and four on the chilled pipe.
Once the flow had stopped, in between the freeze jackets, our engineers cut two new T’s on to the existing LTHW and chilled pipework.
The pipework was then extended inside.
For new servicing, our engineers supplied and installed two new 2.5” Butterfly Valves inside of the building for future use.
The pipework was then allowed to thaw, and we carried out the necessary safety checks.
Result –
Everything was left in good working order.
Our engineers left the site clean and tidy, with all redundant parts being disposed of at a licensed refuse/recycling facility.
Lastly, the client was happy that in the future they can add a new line.
Can we help you with your next project? Discover further details on IDWe Ltd’s Pipe Freezing Services
Get a quote, please call 020 8302 7644 or email info@idwe.co.uk
Find out more about all of IDWe Ltd’s Services
Would you like to keep up to date with our latest news & projects? Follow us on social media: Facebook, X & LinkedIn